Rural Infrastructure : New Cyclone Shelter 45 Nos : Rehab Cyclone Shelter 20 Nos : Critical rural Rd connectivity 80 km
Urban Infrastructure: Upgrade/Rehab. urban Rd. 32 km : side drains 6.8 km : Three footbridges Bridge 20 m
Drains 39.71 km : Water supply : Rehab and improv of existing water produciton facilities : expansion 25 km, replacement 15 km and leak reparis 40 km of water distribution network, provision of 6000 Nos water meter, service connections 5000 no, construction 1 Nos of puphouse for PTW-5, rehab 4 nos pumphouses and rehab of accounts room house 1 nos, provision of chlonination units 15 nos and water quality test kits 6, const. of hand tube well 200 nos. Sanitation & Solid Waste Management LS
Slum Improvements : Foothpath & side drains 2895 m, 1515 meter of footpath drainage and 155 meter of wall/palisades beside water bodies.
CReLIC will act as a knowledge and information hub to collect, process and provide knowledge and exchange of information on climate resilient infrastructure to and from LGED Engineers,institutions and agencies.
Direct benefit : CRIM project increases adaptive capacity of more than 134,000 people to climate change.
Indirect benefit : 10.4 million people (6.8 percent of the total population of the country) will benefit from climate resilient infrastructure planning and implementation in the long term.
Direct co-benefits : creation of more than 1,700 full-time jobs , education support to more than 18,000 children and the reduction of local transport costs by an estimated average of more than 20 percent .

Urban Piloting

Under Component 3 "Pilot climate-resilient urban infrastructure measures in the City of Satkhira (Satkhira Pourashava/Muncipality), the CRIM Project foresees improvements to drainage, flood protection, sanitation, water supply and transport infrastructure with priority given to the most vulnerable such as the inhabitants of city slums."

Capacity Building under 3. will be allocated exclusively to Satkhira Pourashava

Activity Measures of Sub-components (only investments)
Urban Roads Upgrading and rehabilitation of 32 km of urban roads, including 6.8 km of side drains
Bridges Upgrading and rehabilitation of three 20m footbridges
Urban Drains Construction of 39.71 km of urban tertiary and secondary drains
Water Supply Rehabilitation and improvement of existing water production facilities; expansion (25 km), replacement (15 km) and leak repairs (40 km) of Water Distribution Newwork (pipelines); provision of water meters (6,000 no) and service connections (5,000 No); construction (1 No) of pumphouse for PTW-5; rehabilitation of pumphouses (4 No) and rehabilitation of Accounts Room House (1 No); provision of chlorination units (15) and water quality test kits (6); construction of hand tube wells (200 No);
Sanitation Based on locally adapted sanitation concepts; Rehabilitation of 6 Public Toilets and 4 Community Latrines; Provision of material for 2000 pit latrines; Construction of shared latrines (100 No), school latrines (65) and cluster/community latrines (50) and public toilest (5 No) with water supply; provision of 2 No standard quality vacu-tac for fecal sludge collection;
Solid Waste Management Provision of 18,000 pastic-bins for household; provision of 100 wheelbarrows; provision of 150 plastic bins for public places; Provision of 120 uniforms & personal protective equipment for waste collectors and waste workders; construction of 60 RCC bins in slum areas; construction of 5 (average 18 sqmA) transfer stations; provision of 1 garbage truck and 2 trailers with tractor for waste handing;
Slum Improvements 2,895 meter of footpath in nine different slums, 1,515 meter of footpath drainage and 155 meter of walls/palisades beside water bodies;
O&M Fund O&M pilot matching fund of at least 0.3 million EUR.

Total Project Cost

GoB 25 Million Dollar
KfW 15 Million Dollar
GCF 40 Million Dollar
Total 80 Million Dollar